hey everyone sorry we have been so distracted getting the house going i havent posted in ages.

The house is well and truely underway now. Our slab has been poured, frame erected, roofing is on and the windows are in. Our bricklayers have started on the house and have completed our 2 internal double brick blade walls that act as the anchor point and main feature of the entry area.

The termite protection gets put in today and that should let the bricklayers get back to our site next week to finish off all the surrounding walls.

The plumber should also be on site next week to lay all the pipes in our internal walls. The electrical rough in has also been completed. I will post some photos of it soon.

Also No we arnt building in Inverliegh but close to Teesdale. I think many of the small towns around the area have a pretty similar feel and look to them.

Whats even better is we are running on budget, all be it slightly behind schedule but still on target which is good.